Cash flow

Aggregated from transactions · nothing is entered here · values in US$ (budget · RN-04)
Income to date
US$ 1,579,700
Jan–Jul 2026 · Phase I
Expenses to date
US$ 1,093,500
Spent against budget
Cash balance
US$ 486,200
Income − expenses
Balance vs budget
US$ 541,500
Available = budget − spent · AC-14

Expenses by line item × month · Phase I

≤85% budget 85–100% >100%
Line item Apr May Jun Jul Spent Budget % progress
2.1 · Earthworks 48,00052,20045,00042,000 187,200180,000 104%
3.1 · Reinforced concrete 92,400104,00088,00037,500 386,400420,000 92%
4.1 · Labor 70,00072,40068,30070,000 341,700510,000 67%
1.1 · Professional fees 8,0008,0008,0008,000 96,000160,000 60%
5.2 · Plumbing 12,00014,50016,00015,500 58,000145,000 40%
6.1 · Finishes ——6,20018,000 24,200220,000 11%
Total expenses Ph I 230,400251,100231,500191,000 1,093,5001,635,000 67%

Income by source · Phase I

SourceTo date% of total
Sale collectionsUS$ 769,70049%
Bank loans (Banco Austral)US$ 450,00028%
Partner contributionsUS$ 320,00020%
Rentals + extrasUS$ 40,0003%
Total income Ph IUS$ 1,579,700100%

Budget control

Earthworks · 104%
Overspent by US$ 7,200. Needs a budget adjustment or review.
Reinforced concrete · 92%
Close to the cap. US$ 33,600 of budget left.

Rule: yellow >85% · red >100% of budget (AC-15). The same alerts appear on the dashboard.